Question: Draw network diagram, all possible paths and slacks Task Predecessor(s) Duration (weeks) A - 1 B A 4 C A 2 D B 2 E
Draw network diagram, all possible paths and slacks
| Task | Predecessor(s) | Duration (weeks) |
| A | - | 1 |
| B | A | 4 |
| C | A | 2 |
| D | B | 2 |
| E | C | 1 |
| F | D, E | 1 |