Question: Draw network diagram and all possible paths and slacks Task Predecessor(s) Duration (days) A A 12 B A,B 20 C C 11 D C 11
Draw network diagram and all possible paths and slacks
| Task | Predecessor(s) | Duration (days) |
| A | A | 12 |
| B | A,B | 20 |
| C | C | 11 |
| D | C | 11 |
| E | A,E | 4 |
| F | D, E | 2 |