Question: Draw out the project duration You are an Operations Manager at Rachel Software Development and your client has asked you to complete the following project
Draw out the project duration
You are an Operations Manager at Rachel Software Development and your client has asked you to complete the following project in eight days.
| Task | Predecessors | Normal Time (days) | Crash Time (days) | Normal Cost ($) | Crash Cost ($) |
| A | - | 4 | 2 | 500 | 700 |
| B | - | 3 | 2 | 350 | 600 |
| C | A,B | 2 | 1 | 600 |
800 |
| D | B | 3 | 1 | 400 | 1000 |
| E | D | 3 | 2 | 250 | 500 |
| F | C | 4 | 3 | 600 | 900 |
| G | B | 7 | 6 | 500 | 600 |
Rachel Software Development
Duration: Based on Normal Task Times, what is the current estimated duration of the project? 18 days (round to nearest whole day)
Budget: Based on Normal Task Times and Normal Costs, what is the current estimated project budget? (round to nearest whole dollar)
Crash Cost: What is the additional cost to "crash" the project to achieve a duration of eight days? enter your response here (round to nearest whole dollar)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts