Question: Draw project network from the table using AON method , filling the ES, EF, LS, LF and slack for each node. Task Time (days) Immediate

Draw project network from the table using AON method, filling the ES, EF, LS, LF and slack for each node.

Task

Time (days)

Immediate predecessors

A

3

-

B

2

A

C

6

A

D

2

C

E

3

A

F

3

B

G

5

C

H

1

C

I

1.5

F,H

J

2

I