Question: MUAHUL Consider the following tasks for a project. Task Time (days) Immediate predecessors A 3 B 2 6 A D 2 E 3 A F

MUAHUL Consider the following tasks for a

MUAHUL Consider the following tasks for a

MUAHUL Consider the following tasks for a project. Task Time (days) Immediate predecessors A 3 B 2 6 A D 2 E 3 A F 3 B G 5 1 1.5 F.H J 2 I Valmimic COMOO Draw project network from Problem 1 using AON method, filling the ES, EF, LS, LF and slack for each node