Question: Draw the activity network diagram for this problem (either AON or AOA) [5 marks] Determine the Expected Time and Variance for each activity . It
- Draw the activity network diagram for this problem (either AON or AOA) [5 marks]
- Determine the Expected Time and Variance for each activity. It is not given you must determine it [3 marks]
- Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table). [4 marks]
- Determine and state the critical path for this project. This must be based on your work in (c) and not by inspection. [2 marks]
- What are the expected time and the variance of the project? [2 marks]
- What is the probability the project will be completed inless than 32 weeks? [2 marks]
- What time should be set such that there is a 95% chance of completion? [2 marks]
| activity | immediate predecessors | (A) | (M) | (B) |
| A | - | 3 | 6 | 8 |
| B | A | 5 | 8 | 10 |
| C | A | 5 | 6 | 8 |
| D | B,C | 1 | 2 | 4 |
| E | D | 7 | 11 | 17 |
| F | D | 7 | 9 | 12 |
| G | D | 6 | 8 | 9 |
| H | F,G | 3 | 4 | 7 |
| I | E,F,H | 3 | 5 | 7 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock