Question: PROJECT 4 Activity Immediate Predecessors (a) (m) (b) A 0 3 6 8 B A 5 8 10 C A 5 6 8 D B,

PROJECT 4

Activity

Immediate Predecessors

(a)

(m)

(b)

A

0

3

6

8

B

A

5

8

10

C

A

5

6

8

D

B, C

1

2

4

E

D

7

11

17

F

D

7

9

12

G

D

6

8

9

H

F, G

3

4

7

I

E, F, H

3

5

7

  1. Draw the activity network diagram for this problem (either AON or AOA) [5 marks]
  2. Determine the Expected Time and Variance for each activity. [3 marks]
  3. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table). [4 marks]
  4. Determine and state the critical path for this project. This must be based on your work in (c) and not by inspection. [2 marks]
  5. What are the expected time and the variance of the project? [2 marks]
  6. What is the probability the project will be completed in less than 32 weeks? [2 marks]
  7. What time should be set such that there is a 95% chance of completion? [2 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!