Question: Draw the activity network representation for the project given in Table Q.5A and compute the following: i) Identify the critical path and its duration for

Draw the activity network representation for the project given in Table Q.5A and compute the following: i) Identify the critical path and its duration for the given project. ii) Identify slack time of task T3, T6 and T11. iii) Identify latest finish time of Task T5. iv) Identify latest start time of Task T10. Table Q.5A. . Task Duration(days) Dependencies name T1 15 T2 20 T3 25 T1 T4 10 T1 T5 15 T2 T6 20 T2 T7 20 T4, T5 T8 30 T4, T5 T9 15 T4, T5 T10 10 T3,17 T11 20 T6,19