Question: From the following logic table draw an AON network diagram to calculate the normal project duration of the project and identify the critical path: (a)

From the following logic table draw an AON network diagram to calculate the normal project duration of the project and identify the critical path: (a) Your projects' director has asked you to calculate the most economical method to reduce the project duration by 4 weeks and report on the increased cost. Perform a crashing exercise in the most economical order clearly stating: (i) The activity to be crashed and the crash cost. (ii) The project duration after each crash. (iii) The project cost after each crash. (iv) The final critical path(s). (b) Draw a final crash slope, illustrating the financial consequences of each crash