Question: Question 1 a) From the following logic table draw an AON network diagram to calculate the normal project duration of the project and identify the
Question 1
a) From the following logic table draw an AON network diagram to calculate the normal project duration of the project and identify the critical path:
| Activity | Dependency | Normal Duration (weeks) | Normal Cost ($) | Crash Duration (weeks) | Crash Cost ($) |
| A | - | 4 | 500 | 3 | 650 |
| B | A | 3 | 100 | 3 | 100 |
| C | A | 5 | 300 | 3 | 360 |
| D | B | 4 | 200 | 2 | 280 |
| E | A,B | 3 | 350 | 1 | 470 |
| F | C | 4 | 50 | 2 | 100 |
| G | D,E,F | 2 | 650 | 1 | 725 |
b)Draw a Gantt chart for activities A G.
c) Do crashing to reduce the project duration by 5 weeks. Show steps.