Question: Draw the AON project network using the following information: ACTIVITY IMMEDIATE PREDECESSOR(S) DURATION (WEEKS) A 4 B A 3 C A 6 D B 2
Draw the AON project network using the following information:
| ACTIVITY | IMMEDIATE PREDECESSOR(S) | DURATION (WEEKS) |
| A | 4 | |
| B | A | 3 |
| C | A | 6 |
| D | B | 2 |
| E | B | 3 |
| F | C,D | 5 |
| G | E,F | 1 |
|
|
|
|
- Draw an AON diagram of the project, including activity durations.
- What are the different parts and their duration?
- Define the critical path, listing all critical activities in chronological order.
- What is the project duration (in weeks)?
- What is the slack (in weeks) associated with any and all noncritical paths through the project
- Do a table with the ES, EF, LS, LF, Slack and non-critical activities