Question: Draw the AON project network using the following information How long would it take to complete this project? Which activities are included on the critical
- Draw the AON project network using the following information
- How long would it take to complete this project?
- Which activities are included on the critical path?
| ACTIVITY | IMMEDIATE PREDECESSOR(S) | DURATION (WEEKS) |
| A | 4 | |
| B | 35 | |
| C | 5 | |
| D | A | 9 |
| E | B | 3 |
| F | C,E | 1 |
| G | D | 2 |
| H | F | 3 |
| I | G,H | 15 |
| J | G | 1 |