Question: Question 18 (5 points) Draw the AON (activity-on-node) project network using the following information: Activity Immediate predecessor(s) Duration (weeks) A - 4 B A 3
Question 18 (5 points)
Draw the AON (activity-on-node) project network using the following information:
| Activity | Immediate predecessor(s) | Duration (weeks) |
| A | - | 4 |
| B | A | 3 |
| C | A | 6 |
| D | B | 2 |
| E | B | 3 |
| F | C,D | 6 |
| G | E,F | 2 |
Draw an AON diagram of the project, including activity durations (2marks)
Define the critical path, listing all critical activities in chronological order.
What is the project duration in weeks?
What is the slack (in weeks) associated with any and all non-critical paths through the project?