Question: Question 18 (5 points) Draw the AON (activity-on-node) project network using the following information: Activity Immediate predecessor(s) Duration (weeks) A - 4 B A 3

Question 18 (5 points)

Draw the AON (activity-on-node) project network using the following information:

Activity

Immediate predecessor(s)

Duration (weeks)

A

-

4

B

A

3

C

A

6

D

B

2

E

B

3

F

C,D

6

G

E,F

2

Draw an AON diagram of the project, including activity durations (2marks)

Define the critical path, listing all critical activities in chronological order.

What is the project duration in weeks?

What is the slack (in weeks) associated with any and all non-critical paths through the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!