Question: Draw the Gantt chart and calculate average waiting time using Priority scheduling.Use the same table. 6 Use this table for both Q4 and Q5. Process

Draw the Gantt chart and calculate average waiting time using Priority scheduling.Use the same table. 6 Use this table for both Q4 and Q5. Process Arrival Time Priority Burst time P1 0 5 7 P2 6 4 9 P3 12 7 12 P4 19 2 1 P5 25 3 6 (values are given horizontally)