Question: draw the network Activity Immediate Predecessors Duration ( m ) Duration ( a ) Duration ( b ) A - 1 3 5 B -

draw the network
Activity Immediate Predecessors Duration (m) Duration (a) Duration (b)
A -135
B -123
C A 123
D A 234
E B 3411
F C, D 345
G D, E 146
H F, G 245