Question: Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity: Activity Preceding Activity in Time (Weeks)
| Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity: Activity | Preceding Activity in | Time (Weeks) |
| A | ------------ | 7 |
| B | ------------ | 8 |
| C | ------------ | 6 |
| D | A | 6 |
| E | B | 6 |
| F | B | 8 |
| G | C | 4 |
| H | D, E | 7 |
| I | F, G, H | 3 |