Question: Need help - Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity: Activity Preceding Activity
Need help -
Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity:
| Activity | Preceding Activity | Time (Weeks) |
| A | - | 4 |
| B | - | 6 |
| C | A,B | 7 |
| D | B | 8 |
| E | B | 5 |
| F | C | 5 |
| G | D | 7 |
| H | D,E | 8 |
| I | F,G,H | 4 |