Question: Need help - Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity: Activity Preceding Activity

Need help -

Draw the network and identify the critical path. Also calculate the earliestlatest starting and finishing times for each activity:

Activity

Preceding Activity

Time (Weeks)

A

-

4

B

-

6

C

A,B

7

D

B

8

E

B

5

F

C

5

G

D

7

H

D,E

8

I

F,G,H

4