Question: Draw the network AON for this project Activity Time (hours) Immediate Predecessors A 1.5 NONE B 1.0 NONE C 2.0 A D 1.5 A, B
Draw the network AON for this project
| Activity | Time (hours) | Immediate Predecessors |
| A | 1.5 | NONE |
| B | 1.0 | NONE |
| C | 2.0 | A |
| D | 1.5 | A, B |
| E | 1.0 | C.D |
- What are the ES, EF, LS and LF of the project?
- What is the duration of the project?
- What are the slack times of the activities?
- What is the Critical Path?