Question: Task time estimates for the modification of an assembly process are given in the following table. Activity Time (hours) Immediate Predecessors None A 4 B

Task time estimates for the modification of an
Task time estimates for the modification of an assembly process are given in the following table. Activity Time (hours) Immediate Predecessors None A 4 B 2 A C 9 None D 4. A E 5 B,C,D The critical path for the associated network is time with project completion A-D-E: 13 hours C-E: 14 hours A-B-C-D-E: 22 hours A-B-D; 10 hours A-B-E: 11 hours