Question: Task time estimates for the modification of an assembly process are given in the following table. Activity Time (hours) Immediate Predecessors A 4 None B

Task time estimates for the modification of an
Task time estimates for the modification of an assembly process are given in the following table. Activity Time (hours) Immediate Predecessors A 4 None B 2 A 9 None D 4 A E 5 B,C,D The critical path for the associated network is time with project completion OC.E: 14 hours A-B-E: 11 hours O A-B-C-D-E: 22 hours O A-D-E: 13 hours A-B-D: 10 hours