Question: Draw the network Calculate ES, LS, EF, LF, SLACK, variance of each activity, the expected duration of each activity, and the probability of finishing the

Draw the network Calculate ES, LS, EF, LF, SLACK,

Draw the network Calculate ES, LS, EF, LF, SLACK, variance of each activity, the expected duration of each activity, and the probability of finishing the project 1 week later than expected finish date

Most Optimistic Likely Pessimistic Time (a) Time(m) time(b) Activity Predecessor w > N >> D> N B,C = 1 + 9 goes oor EFD o u N

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!