Question: Draw the Network Chart include task id, duration, ES, EF, LS, LF, slack What is the critical path? What is slack time for tasks F

- Draw the Network Chart include task id, duration, ES, EF, LS, LF, slack
- What is the critical path? What is slack time for tasks F and G?
- Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not?
- Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not?
- What is slack time and lag time?
- Can the critical path of a project change? Why or why not?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
