Question: Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time. table [ [
Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time.
tableActivitytableImmediatePredecessorstableTimeWeeksABCADBEBFC DGD EHG F
tableActivitytableEarliestStartiestLatest,Latest Finish,SlackSinishStart,,,,ABCDEFGH