Question: Draw the network diagram. Activity Immeidate Processor(s) Opptimistic A ____ 5 B _________ 6 C ___________ 3 D A 11 E B 8 F C,E

Draw the network diagram.

Activity Immeidate Processor(s) Opptimistic

A ____ 5

B _________ 6

C ___________ 3

D A 11

E B 8

F C,E 3

G D 4

H F 5

I G,H 8

J G 4