Question: Draw the precedence diagram using PDM for the following project, find all the project paths, identify the Critical Path, and project duration. Activity Predecessor Duration
Draw the precedence diagram using PDM for the following project, find all the project paths, identify the Critical Path, and project duration. Activity Predecessor Duration (Days) A-3 BA7 CA8 DA5 E B,C 4 F C,G 2 GD6 HF4 I E,F 3 J H,I 1