Question: Draw the precedence network and perform the network calculation ( using only the most likely duration ) . 2 . Determine the critical path. 3

Draw the precedence network and perform the network calculation
(
using only the most likely duration
)
.
2
.
Determine the critical path.
3
.
What is the total slack and free slack of activity F
?
4
.
If you need to shorten the critical path by two days, what is the best activity to apply crashing independently of cost
?
5
.
For the activities on the critical path found in item
2
,
calculate the expected duration, standard deviation, and variance.
6
.
Considering the information in item
5
,
what is the project delivery deadline, considering a confidence interval of
9
5
.
4
4
%
?
\
table
[
[
Activity
,
Precedence,
\
table
[
[
Duration
]
,
[
Optimistic
]
,
[
Most Likely
]
]
]
,
[
BEGINNING
,
,
0
,
0
,
0
]
,
[
A
,
BEGINNING,
4
1
,
6
0
,
8
9
]
,
[
B
,
BEGINNING,
1
2
,
2
0
,
2
4
]
,
[
C
,
BEGINNING,
2
8
,
3
0
,
3
3
]
,
[
D
,
A
,
8
5
,
1
0
0
,
1
1
3
]
,
[
E
,
A
,
2
0
,
3
0
,
4
0
]
,
[
F
,
B
,
1
4
,
2
0
,
2
7
]
,
[
G
,
C
,
3
4
,
4
0
,
4
8
]
,
[
H
,
E
,
4
5
,
5
0
,
6
8
]
,
[
J
,
F
,
G
,
6
4
,
8
0
,
8
4
]
,
[
K
,
J
,
2
4
,
4
0
,
4
8
]
,
[
L
,
G
,
4
5
,
6
0
,
7
8
]
,
[
M
,
L
,
1
6
,
2
0
,
2
2
]
,
[
END
,
D
,
H
,
K
,
M
,
0
,
0
,
0
]
]
NOTE: DATA IN HOURS. ONE DAY EQUIVALENT TO
8
HOURS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!