Question: Draw the schedule AON activity on node network format. for the below project Schedule : analyze the network using the manual method to determine ES,
Draw the schedule AON "activity on node" network format. for the below project Schedule:
- analyze the network using the manual method to determine ES, LS, EF, LF;
- calculate float for each activity; and
- identify the critical path.
- ensure that your calculations are clearly identified on the diagram using the following legend for your nodes:
project Schedule:
| Item# | Task | Duration | Predecessor | |
| 1 | FLYHIGH AIRLINES PROJECT | |||
| 2 | Project Approval | 2W | ||
| 3 | Obtain Approval | 2w | ||
| 4 | Building | 37W | ||
| 5 | Design Test Cell Building | 12W | 3 | |
| 6 | Tenders & Construction | 25W | 5 | |
| 7 | Test Cell Equipments (delivery, installation) | 48W | ||
| 8 | The lead time on the test cell equipment | 34W | 3 | |
| 9 | To fit the test cell equipment | 11W | 8 | |
| 10 | shakedown testing before the cell would be ready for engine testing. | 3W | 9 | |
| 11 | Engine Repair shop equipment | 34W | ||
| 12 | the equipment lead time | 29W | 3 | |
| 13 | the equipment installation | 5W | 12 | |
| 14 | Special tools | 24 W | ||
| 15 | The design of special tools | 12W | 3 | |
| 16 | Procurement special tools | 12 W | 15 | |
| 17 | inventory | 43W | ||
| 18 | inventory planning | 8W | 3 | |
| 19 | lead time | 35W | 18 | |
| 20 | Training | 3W | ||
| 21 | The training | 3W | 10 | |
| 22 | Repair and Test process | 9W | ||
| 23 | engine repair and test times | 7W | 21 | |
| 24 | the first engine test of this engine. | 2W | 23 | |
| 25 | Finish | 0 W | 24 | |