Question: Draw the updated network. Calculate the new project completion date, Check if there are changes to the completion date and / or to the critical
Draw the updated network. Calculate the new project completion date, Check if there are changes to the completion date andor to the critical path,
Refer to Exercise in Chapter Twelve days after the start of the project, the following information is received:
tableActivities A and DCompleted on timeActivity BCompleted by end of day Activity CStarted on time; finished day lateActivity Not started yetActivity FDuration changed to daysActivity GCanceledActivity I,Started; day left
A change order was issued with three new activities:
tableActivity Duration days; IPA None, Successor Activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
