Question: Question 1 : Refer to the network below Baseline schedule table [ [ Activity , Duration,IPA,ES , EF , LS , LF , TF
Question :
Refer to the network below
Baseline schedule
tableActivityDuration,IPA,ESEFLSLFTFFFABCDA BEBFDGD EHC FIC GJH I,
Fifteen days after the start of the project, the following information is received.
Activity A Completed days later than planned
Activity B Completed on time
Activity C Started; days left
Activity D Completed; took days to finish
Activity E Completed
Activity F Canceled
Activity G Started days late; project manager hopes to cut day of its duration
Activity K Added: Duration days. IPA
Activity L Added: Duration days. IPA
Activity I Adjusted: IPA L
Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date andor to the critical path. Mention the causes for such changes, if any.
Rubric:
New network based on the new information received after days Correct calculations, professionally done points
Mention if critical path changes or extended points
Write causes for change in critical path or extension in the critical path points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock