Question: Drawing PERT diagram. Example Activity Description Predecessors Time required A Select office site none 3 B Create org. and financial plan none 5 Determine personnel

Drawing PERT diagram.
Example Activity Description Predecessors Time required A Select office site none 3 B Create org. and financial plan none 5 Determine personnel requirements lucem B 3 D Design facility A, C 4 E Construct interior D 8 F Select personnel to move AC 2 G Hire new employees F 4 H Move records, key personnel, etc F 2 1 Train new personnel E, G, H 3