Question: Dummy activities O A. are used when two activities have identical starting and ending events. B. cannot be on the critical path. O C. are

Dummy activities O A. are used when two activities have identical starting and ending events. B. cannot be on the critical path. O C. are found in both AOA and AON networks. OD. have a duration equal to the shortest non-dummy activity in the network.
 Dummy activities O A. are used when two activities have identical

Dummy activities A. are used when two activities have identical starting and ending events. B. cannot be on the critical path. C. are found in both AOA and AON networks. D. have a duration equal to the shortest non-dummy activity in the network