Question: ummy activities A . cannot be on the critical path. B . have a duration equal to the shortest non - dummy activity in the

ummy activities
A. cannot be on the critical path.
B. have a duration equal to the shortest non-dummy activity in the network.
C. are used when two activities have identical starting and ending events.
D. are found in both AOA and AON networks.