Question: Duration (Days) 3 Immediate Predecessors Activity A B 2 N 4 A D 5 A,B E 4 4 B F F 4 DE a. The

Duration (Days) 3 Immediate Predecessors Activity

Duration (Days) 3 Immediate Predecessors Activity A B 2 N 4 A D 5 A,B E 4 4 B F F 4 DE a. The Earliest Start Time of Activity D is days. b. The Latest Finish Time of Activity C is days. C. The Latest Finish Time of Activity Ais days. d. The critical path is with a project duration of days. (Please input letters only without spaces for the critical path. For example, if the critical path is A-B- C, please input ABC.)