Question: Duration (days) Activity Predecessor Optimistic Most Likely Pessimistic A * 3 5 13 B * 4 7 10 C A 5 7 15 D B

Duration (days)

Activity

Predecessor

Optimistic

Most Likely

Pessimistic

A

*

3

5

13

B

*

4

7

10

C

A

5

7

15

D

B

8

9

22

What is the probability that this project will be completed within 22 days?