Question: Duration (days) Task Description Predecessor 1 Identify project 2 2 Hire staff 1 3 3 Design solution 1 5 Train staff 2,3 4 5

Duration (days) Task Description Predecessor 1 Identify project 2 2 Hire staff 1 3 3 Design solution 1 5 Train staff 2,3 4 5 Deploy solution 3 3 Train customer 4,5 3 1) Draw the AON network. 2) Determin the earliest and Latest activty start and finsh times. 3) Determine the slack for each activity. 4) identify the critical path. 5) How long will the project take. Critical path answer Project duration answer ES DE 15 Key Task # EF LF