Question: Duration (days) Task Description Predecessor 1 Identify project 2 2 Hire staff 1 3 3 Design solution 1 5 Train staff 2,3 4 5

Duration (days) Task Description Predecessor 1 Identify project 2 2 Hire staff

 

Duration (days) Task Description Predecessor 1 Identify project 2 2 Hire staff 1 3 3 Design solution 1 5 Train staff 2,3 4 5 Deploy solution 3 3 Train customer 4,5 3 1) Draw the AON network. 2) Determin the earliest and Latest activty start and finsh times. 3) Determine the slack for each activity. 4) identify the critical path. 5) How long will the project take. Critical path answer Project duration answer ES DE 15 Key Task # EF LF

Step by Step Solution

3.37 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer Solution B TASKS T1 T2 T3 T4 T5 T6 0 0 2 T2 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Leadership Questions!