Question: DURATION ESTIMATES (Weeks) ACTIVITY PRECEDES Start A, B OPTIMISTIC MOST LIKELY PESSIMISTIC A C, D 3 5 7 B D 4 7 9 C E
DURATION ESTIMATES (Weeks) ACTIVITY PRECEDES Start A, B OPTIMISTIC MOST LIKELY PESSIMISTIC A C, D 3 5 7 B D 4 7 9 C E 3 4 5 D F 4 5 6 E F 5 7 9 F End 3 6 9.
Draw PERT/CPM diagram for this project.