Question: During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job
During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job was completed on December 15, 2021. Additional data are as follows:
2020 2021
Actual costs incurred $405,000 $457,000
Estimated remaining costs 405,000
Billings to date 360,000 690,000
Collections to date 200,000 480,000
For 2021, what amount should Bing recognize as gross profit?