Question: Problem 12 Chandler Limited started a construction job with a total contract price of $ 1,050,000 during 2020. Chandler uses the completed contract method. The
Problem 12 Chandler Limited started a construction job with a total contract price of $ 1,050,000 during 2020. Chandler uses the completed contract method. The job was completed on December 21, 2021. Additional data is as follows:
2020 2021 Actual costs incurred $ 405,000 $ 457,500 Estimated remaining costs 405,000 Billings to date 360,000 690,000 Collections to date 200,000 480,000
What amount should Chandler recognize as gross profit in 2020?
Problem 12 options:
a)
$ 0
b)
$ 120,000
c)
$ 142,500
d)
$ 187,500
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts