Question: During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800,000. Which approach should the risk manager suggest the project manager take? Sensitivity analysis Quanttatve analysis Simulation analysis Monte Carlo simulation