Question: During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800,000. Which approach should the risk manager suggest the project manager take? Simulation analysis Monte Carlo simulation Sensitivity analysis Quantitative analysis

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!