During an iteration planning session, the product owner disagreed with one of the team members on story points assigned to a story. The discussion became heated, and no agreement could be reached. What is the next step?
The point estimates from the team member is the only value that matters
The Scrum Master can decide who has it right
The point estimate from the product owner is more important, and that should be used.
The average of their point estimates should be used.