Question: During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takett on a negative variance. Which calculation is the project manager

During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takett on a negative variance. Which calculation is the project manager likely to use as a measurement tool to validate this information? O EV - PV O EVAC O EV/PV O EV - Ac