estion 2 5 points Saw During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takes on a negative variance. Which calculation is the project manager likely to use as a measurement tool to validate this information? EV.PV EVAC EV/PV EV- AC