Question: During risk management activities, 2 3 6 risks have been identified which are caused by 1 3 root causes. You could eliminate the 2 3

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For the remaining 2 risks, you and your team could not find a way to mitigate or insure the risks. Also, these 2 risks cannot be outsourced or removed from the project scope. What is the best solution?
Question 17Answer
a.
Avoid the risk
b.
Accept the risk
c.
Mitigate the risk
d.
Transfer the risk