Question: During risk management activities, 2 3 6 risks have been identified which are caused by 1 3 root causes. You could eliminate the 2 3
During risk management activities, risks have been identified which are caused by root causes. You could eliminate the risks by your risk management activities. For the remaining risks, you and your team could not find a way to mitigate or insure the risks. Also, these risks cannot be outsourced or removed from the project scope. What is the best solution?
Question Answer
a
Avoid the risk
b
Accept the risk
c
Mitigate the risk
d
Transfer the risk