Question: During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk
During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also these 2 risks cannot be outsourced or removed from project scope. What is the best solution for this situation and explain.