Question: During sprint execution, when are new sprint tasks added? Group of answer choices As soon as possible after they are identified, unless they reflect a
During sprint execution, when are new sprint tasks added?
Group of answer choices
As soon as possible after they are identified, unless they reflect a scope change in the sprint goals or committed product backlog items
When the Scrum Master approves them
Never. The sprint tasks are fixed and decided during sprint planning
When the product owner identifies a new task
When the Scrum Master identifies a new task