Question: During the 1 9 4 0 s , line managers functioned as project managers and used the concept of over - the - fence management
During the s line managers functioned as project managers and used the concept of overthefence management to manage projects. This meant that each line manager, acting as a project manager, would perform the work necessitated by his or her line organization and when that was completed, would throw the ball, or that part of their project, over the fence in the hope that someone would catch it and take over the next phase of the project.
Group of answer choices
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock