Question: E Activity Optimistic Most Likely Pessimistic Expected Time Variance B 3 1 START 0 0 0 A 6 10 14 1.78 G 2 B

E Activity Optimistic Most Likely Pessimistic Expected Time Variance B 3 1START 0 0 0 A 6 10 14 1.78 G 2 B

E Activity Optimistic Most Likely Pessimistic Expected Time Variance B 3 1 START 0 0 0 A 6 10 14 1.78 G 2 B 0 1 2 0.11 2 1 A START FINISH C 16 20 30 5.44 10 D 3 5 7 0.44 E 2 3 4 0.11 2 C 21 F 10 13 1 G 1 2 3 0.11 F 10 H 2 4 0.44 2 2 2 3 4 0.11 K 0 1 2 0.11 L 1 2 3 0.11 FINISH 0 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!