Question: e ) Using the Critical Ratio ( CR ) scheduling rule for sequencing the jobs, the order is: Part 3 0 Part 3 1 Part
e Using the Critical RatioCR scheduling rule for sequencing the jobs, the order is:
Part Part Part
Sequence
Job
A
B
D
C
B
D
A
C
D
A
C
B
C
B
D
A
Part
The average tardinessjob lateness for the sequence developed using the CR rule
enter your response here days round your response to two decimal places
Part
The average completion timeflow time for the sequence developed using the CR rule
enter your response here days round your response to two decimal places
Part
The percentage utilization for the sequence developed using the CR rule
enter your response hereenter your response as a percentage rounded to two decimal places
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock