Question: EAC= D36/K34 ETAC= D37/L34 TASK TOTAL BUDGET % COMP ACWP (AC) BCWS (PV) BCWP (EV) CV SV CPI SPI A B D 100% 30% 70%

EAC= D36/K34 ETAC= D37/L34 EAC= D36/K34 ETAC= D37/L34 TASK TOTAL BUDGET %
EAC= D36/K34 ETAC= D37/L34 TASK TOTAL BUDGET %
TASK TOTAL BUDGET % COMP ACWP (AC) BCWS (PV) BCWP (EV) CV SV CPI SPI A B D 100% 30% 70% 80% 0% 40% 0% E F G Totals SO BAC - TAC Comments: EAC ETAC- NOIV/01 DIV/0! B/9 E/9 A/8 C/7 G/4 F/7 D/6 Assume the project is 14 days old. TASK Percent Complete Expenditures/ Day Duration 100% 30% 70% 80% $2,000 $3,000 $2,000 $1,500 $1,500 $1,000 $1,200 Actual Expenditures to Date $10,000 $9,000 $4,000 $5,000 $3,000 $0 $0 ON000 9 0% 40% 7 4 0%